2 weeks to complete structure and envelope. 

After two weeks of work, the structure and envelope of facades, roofs, and slabs of a single-family home are finished.

Location: Gilet.

Project Phase: Design, structural calculation justification, and manufacturing.

Week 1: Structure installed in 7 workdays.


Description: The structure of this residence has been installed in 7 workdays.
The challenge was to build on a steeply sloped terrain where access, stockpiling, and material handling were truly complex.
Thanks to the lightweight nature of our steelframe system, this has been achieved in record time and with minimal resources for lifting equipment.

The next phase: Enveloping of facades, roofs, and slabs, started simultaneously with the final phase of structural assembly, will be executed using THERMOCHIP’s dry panel system.